SpencerCity News

10/11/2021 Update – Tentative Schedule – 2021 4th Street HMA Overlay Project

10/11/2021 Update – Tentative Schedule – 2021 4th Street HMA Overlay Project

  •  Pillar Inc continued working on curb & gutter replacement on West 4thStreet between 2nd and 3rd Avenue W this week .  They will work on completing the Curb and Gutter west of Grand Avenue during the first part of next week and then move to the east side of Grand Ave to start that concrete work.

Asphalt milling operation started on Thursday on E 4th Street between Grand Ave and 5th Avenue East.  They continued today milling on W 4th Street between Grand Avenue and 5th Avenue West.  The tentative paving plan is to start the intermediate course next Wednesday.  The remaining milling between 6th Avenue West and 11th Avenue West will also be scheduled for sometime next week.  We will communicate the updated schedule when we hear more from the Contractor.